April 8, 2022

Date: April 8, 2022 Key Achievements Level 4 suspended slab North-East GL. 4 –7 (B –F+) -Complete Level4 core walls and columns completed On-going Damp proofing Level 5 suspended slab Level 4 North-East Core wall and columns Level 3 North-West Upstand walls Mechanical and Electrical slab rough-ins