June 2022
Schedule Progress Damp proofing – 95% Complete. Level 6 suspended slab North – On-going Level 6 suspended slab South – On-going Backfilling – On-going Upstand walls – On-going Curtain walls Levels 1&2 CRU’s – On-going Steel Studs Levels 1 – 4 – On-going Brickwork Parkade – On-going Key Achievement Level 5 North East core […]