July 2022
Schedule Progress • Damp proofing – 95% Complete.• Level 6 North Core walls and Columns – On-going• Roofing South formwork – On-going• Roofing North formwork – On-going• Backfilling – On-going• Upstand walls – On-going• Curtainwalls glazing Levels 1 and 2 CRU’s – 93% complete.• Curtainwalls framing & Spandrel levels 3 and 4 North – On-going• […]