Schedule Progress
  • Roof upstand and Parapet walls North – On-going
  • Backfilling – On-going
  • Upstand walls – On-going
  • Curtainwalls glazing & Spandrel levels 3 and 4 South Courtyard – On-going
  • Steel Studs Levels 1 – 5 North – On-going
  • Exterior soffit steel stud framing North – On-going
  • Exterior denseglass sheeting Levels 1 – 5 North – On-going
  • Mechanical Rough-ins Parkade – Levels 5 – On-going
  • Electrical Rough-ins Parkade – Levels 5 – On-going
  • Exterior and Parkade soffit membrane North – On-going
  • Steel Stud furring of columns and walls CRU 4 South – On-going
Key Achievement
  • Suspended Roof Slab – Complete
Look Ahead
  • Roofing Membrane Completion – October 11th
  • TI Level 5 interior steel stud installation starting September 19th
Current Photos
Key Activities

Activities

Baseline Start Date

Baseline Finish Date

Revised Start Date

Revised Finish Date

Remarks

Steel Studs Framing Levels 1 – 6

04/26/22

09/08/22

05/10/22

10/14/22

In-progress

Curtain walling Levels 1 – 6

02/21/22

05/10/22

04/29/22

10/21/22

In-progress

Plaster & Gypsum Board Install (BB)
Levels 1 – 6

 

 

08/12/22

10/20/20

In-progress

Membrane Roofing

09/08/22

09/22/22

09/20/22

10/11/22

In-progress