Schedule Progress
- Membrane Roofing – On-going
- Backfilling – On-going
- Level 6 upstand walls – On-going
- Curtainwalls glazing & Spandrel level 5 North and South Courtyard – On-going
- Steel Studs Levels 5 South – On-going
- Exterior soffit steel stud framing North – Nearing completion
- Exterior denseglass sheeting Level 5 South – On-going
- Mechanical Rough-ins Parkade – Levels 6 – On-going
- Electrical Rough-ins Parkade – Levels 6 – On-going
- Exterior and Parkade soffit insulation North – On-going
- Level 5 TI interior steel stud installation – On-going
Key Achievement
- Suspended Roof Slab – Complete
Look Ahead
- Membrane Roofing Completion – October 24th
- Exterior Curtainwall glazing completion – November 15th
Current Photos
Key Activities
Activities | Baseline Start Date | Baseline Finish Date | Revised Start Date | Revised Finish Date | Remarks |
Steel Studs Framing Levels 1 – 6 | 04/26/22 | 09/08/22 | 05/10/22 | 10/14/22 | In-progress |
Curtain walling Levels 1 – 6 | 02/21/22 | 10/21/22 | 04/29/22 | 11/15/22 | In-progress |
Plaster & Gypsum Board Install (BB) |
| 08/12/22 | 11/09/20 | In-progress | |
Membrane Roofing | 09/08/22 | 09/22/22 | 09/20/22 | 10/24/22 | In-progress |