Schedule Progress
  • Membrane Roofing – On-going
  • Backfilling – On-going
  • Level 6 upstand walls – On-going
  • Curtainwalls glazing & Spandrel level 5 North and South Courtyard – On-going
  • Steel Studs Levels 5 South – On-going
  • Exterior soffit steel stud framing North – Nearing completion
  • Exterior denseglass sheeting Level 5 South – On-going
  • Mechanical Rough-ins Parkade – Levels 6 – On-going
  • Electrical Rough-ins Parkade – Levels 6 – On-going
  • Exterior and Parkade soffit insulation North – On-going
  • Level 5 TI interior steel stud installation – On-going
Key Achievement
  • Suspended Roof Slab – Complete
Look Ahead
  • Membrane Roofing Completion – October 24th
  • Exterior Curtainwall glazing completion – November 15th
Current Photos
Key Activities

Activities

Baseline Start Date

Baseline Finish Date

Revised Start Date

Revised Finish Date

Remarks

Steel Studs Framing Levels 1 – 6

04/26/22

09/08/22

05/10/22

10/14/22

In-progress

Curtain walling Levels 1 – 6

02/21/22

10/21/22

04/29/22

11/15/22

In-progress

Plaster & Gypsum Board Install (BB)
Levels 1 – 6

 

 

08/12/22

11/09/20

In-progress

Membrane Roofing

09/08/22

09/22/22

09/20/22

10/24/22

In-progress