Schedule Progress
Membrane Roofing – On-going
Curtainwalls glazing & Spandrel level 5 South East – On-going
Mechanical Rough-ins Parkade – Levels 6 – On-going
Electrical Rough-ins Parkade – Levels 6 – On-going
Exterior soffit insulation South – On-going
Level 5 TI interior steel stud installation – On-going
Level 5 TI Mechanical and Electrical Rough ins – On-going
Key Achievement
Exterior Denseglass sheeting level 5 – Complete
Roof waterproofing – Complete
Level 6 upstand walls – Complete
Look Ahead
• MembraneRoofingCompletion- November30th
• Exterior Curtainwall glazing L6 completion – November 30th
Current Photos
Key Activities
Activities | Baseline Start Date | Baseline Finish Date | Revised Start Date | Revised Finish Date | Remarks |
Steel Studs Framing Levels 1 – 6 | 04/26/22 | 10/14/22 | 05/10/22 | 11/15/22 | In-progress |
Curtain walling Levels 1 – 6 | 02/21/22 | 10/21/22 | 04/29/22 | 11/30/22 | In-progress |
Plaster & Gypsum Board Install (BB) |
| 08/12/22 | 11/30/20 | In-progress | |
Membrane Roofing | 09/08/22 | 09/22/22 | 09/20/22 | 11/28/22 | In-progress |