Schedule Progress
Suspended roof slab North-West reinforcement – On-going
• Suspended roof upstand walls North-East – On-going
• Backfilling – On-going
• Upstand walls – On-going
• Curtainwalls glazing Levels 1 and 2 CRU’s – 95% Complete.
• Curtainwalls glazing & Spandrel levels 3 and 4 North – On-going
• Steel Studs Levels 1 – 5 North – On-going
• Mechanical Rough-ins – On-going
• Electrical Rough-ins – On-going
Key Achievement
• Suspended Roof Slab South and North-East – Complete
Look Ahead
• Aluminum Composite Panel Installation – Starting August 29th
• Suspended Roof slab North-West completion – August 24th
Current Photos
Key Activities
Activities | Baseline Start Date | Baseline Finish Date | Revised Start Date | Revised Finish Date | Remarks |
Steel Studs Framing Levels 1 – 6 | 04/26/22 | 09/08/22 | 05/10/22 | 10/14/22 | In-progress |
Curtain walling Levels 1 – 6 | 02/21/22 | 05/10/22 | 04/29/22 | 10/21/22 | In-progress |
Suspended Roof Slab | 06/05/22 | 06/17/22 | 07/21/22 | 08/24/22 | On-track |
Plaster & Gypsum Board Install (BB) |
|
| 08/12/22 | 10/20/20 | In-progress |
Membrane Roofing | 09/08/22 | 09/22/22 | 09/20/22 | 10/11/22 | Not started |