Schedule Progress

Suspended roof slab North-West reinforcement – On-going
• Suspended roof upstand walls North-East – On-going
• Backfilling – On-going
• Upstand walls – On-going
• Curtainwalls glazing Levels 1 and 2 CRU’s – 95% Complete.
• Curtainwalls glazing & Spandrel levels 3 and 4 North – On-going
• Steel Studs Levels 1 – 5 North – On-going
• Mechanical Rough-ins – On-going
• Electrical Rough-ins – On-going

Key Achievement

• Suspended Roof Slab South and North-East – Complete

Look Ahead

• Aluminum Composite Panel Installation – Starting August 29th
• Suspended Roof slab North-West completion – August 24th

Current Photos
Key Activities

Activities

Baseline Start Date

Baseline Finish Date

Revised Start Date

Revised Finish Date

Remarks

Steel Studs Framing Levels 1 – 6

04/26/22

09/08/22

05/10/22

10/14/22

In-progress

Curtain walling Levels 1 – 6

02/21/22

05/10/22

04/29/22

10/21/22

In-progress

Suspended Roof Slab

06/05/22

06/17/22

07/21/22

08/24/22

On-track

Plaster & Gypsum Board Install (BB)
Levels 1 – 6

 

 

08/12/22

10/20/20

In-progress

Membrane Roofing

09/08/22

09/22/22

09/20/22

10/11/22

Not started