- Schedule Progress
- Damp proofing – 95% Complete.
- Level 6 suspended slab North-West – On-going
- Level 6 suspended slab South – On-going
- Backfilling – On-going
- Level 3 Upstand walls – On-going
- Curtain walls Levels 1&2 CRU’s – On-going
- Steel Studs Levels 1&2 – On-going
- Brickwork level P3&P2 – On-going
- Key Achievement
- Level 5 suspended slab North-East – Complete
- Level 5 North East core wall 2 and columns – Complete
- Look Ahead
- Level 6 Suspended slab North-West and South – Completion June 14th (Delayed 3 weeks due to additional works associated with Electrical installation for TI scope of works
and SI 59 Planter Boxes) - Level 6 Columns and Core Walls – Completion June 28th
- Level 6 Suspended slab North-West and South – Completion June 14th (Delayed 3 weeks due to additional works associated with Electrical installation for TI scope of works