• Schedule Progress
    • Damp proofing – 95% Complete.
    • Level 6 suspended slab North-West – On-going
    • Level 6 suspended slab South – On-going
    • Backfilling – On-going
    • Level 3 Upstand walls – On-going
    • Curtain walls Levels 1&2 CRU’s – On-going
    • Steel Studs Levels 1&2 – On-going
    • Brickwork level P3&P2 – On-going
  • Key Achievement
    • Level 5 suspended slab North-East – Complete
    • Level 5 North East core wall 2 and columns – Complete
  • Look Ahead
    • Level 6 Suspended slab North-West and South – Completion June 14th (Delayed 3 weeks due to additional works associated with Electrical installation for TI scope of works
      and SI 59 Planter Boxes)
    • Level 6 Columns and Core Walls – Completion June 28th