Schedule Progress

• Damp proofing – 95% Complete.
• Level 6 North Core walls and Columns – On-going
• Roofing South formwork – On-going
• Roofing North formwork – On-going
• Backfilling – On-going
• Upstand walls – On-going
• Curtainwalls glazing Levels 1 and 2 CRU’s – 93% complete.
• Curtainwalls framing & Spandrel levels 3 and 4 North – On-going
• Steel Studs Levels 1 – 4 North – On-going
• Brickwork Parkade – On-going
• Mechanical Rough-ins – On-going
• Electrical Rough-ins – On-going

Key Achievement

• Level 6 suspended slab North – Complete
• Level 6 South columns and core walls – Complete

Look Ahead

• Level 6 Columns and Core Walls – Completion July 15th
• Suspended Roof slab completion – August 5th

Current Photos
Key Activities

Activities

Baseline Start Date

Baseline Finish Date

Revised Start Date

Revised Finish Date

Remarks

Level 6 Suspended Slab

05/07/22

05/21/22

05/17/22

06/29/22

Complete

Steel Studs Framing Levels 1 – 4

02/14/22

04/26/22

04/26/22

07/20/22

In-progress

Curtain walling Levels 1 – 4

02/21/22

05/10/22

04/29/22

08/02/22

In-progress

Level 6 Core walls and Columns

05/22/22

06/04/22

06/29/22

07/20/22

In-progress

Suspended Roof Slab

06/05/22

06/17/22

07/21/22

08/05/22

In-progress