Schedule Progress
• Damp proofing – 95% Complete.
• Level 6 North Core walls and Columns – On-going
• Roofing South formwork – On-going
• Roofing North formwork – On-going
• Backfilling – On-going
• Upstand walls – On-going
• Curtainwalls glazing Levels 1 and 2 CRU’s – 93% complete.
• Curtainwalls framing & Spandrel levels 3 and 4 North – On-going
• Steel Studs Levels 1 – 4 North – On-going
• Brickwork Parkade – On-going
• Mechanical Rough-ins – On-going
• Electrical Rough-ins – On-going
Key Achievement
• Level 6 suspended slab North – Complete
• Level 6 South columns and core walls – Complete
Look Ahead
• Level 6 Columns and Core Walls – Completion July 15th
• Suspended Roof slab completion – August 5th
Current Photos
Key Activities
Activities | Baseline Start Date | Baseline Finish Date | Revised Start Date | Revised Finish Date | Remarks |
Level 6 Suspended Slab | 05/07/22 | 05/21/22 | 05/17/22 | 06/29/22 | Complete |
Steel Studs Framing Levels 1 – 4 | 02/14/22 | 04/26/22 | 04/26/22 | 07/20/22 | In-progress |
Curtain walling Levels 1 – 4 | 02/21/22 | 05/10/22 | 04/29/22 | 08/02/22 | In-progress |
Level 6 Core walls and Columns | 05/22/22 | 06/04/22 | 06/29/22 | 07/20/22 | In-progress |
Suspended Roof Slab | 06/05/22 | 06/17/22 | 07/21/22 | 08/05/22 | In-progress |