• Schedule Progress

    • Membrane Roofing – On-going

    • Curtainwalls glazing & Spandrel level 5 South East – On-going

    • Mechanical Rough-ins Parkade – Levels 6 – On-going

    • Electrical Rough-ins Parkade – Levels 6 – On-going

    • Exterior soffit insulation South – On-going

    • Level 5 TI interior steel stud installation – On-going

    • Level 5 TI Mechanical and Electrical Rough ins – On-going

  • Key Achievement

    • Exterior Denseglass sheeting level 5 – Complete

    • Roof waterproofing – Complete

    • Level 6 upstand walls – Complete

  • Look Ahead
    • MembraneRoofingCompletion- November30th
    • Exterior Curtainwall glazing L6 completion – November 30th

Current Photos
Key Activities

Activities

Baseline Start Date

Baseline Finish Date

Revised Start Date

Revised Finish Date

Remarks

Steel Studs Framing Levels 1 – 6

04/26/22

10/14/22

05/10/22

11/15/22

In-progress

Curtain walling Levels 1 – 6

02/21/22

10/21/22

04/29/22

11/30/22

In-progress

Plaster & Gypsum Board Install (BB)
Levels 1 – 6

 

 

08/12/22

11/30/20

In-progress

Membrane Roofing

09/08/22

09/22/22

09/20/22

11/28/22

In-progress