Schedule Progress
- Roof upstand and Parapet walls North – On-going
- Backfilling – On-going
- Upstand walls – On-going
- Curtainwalls glazing & Spandrel levels 3 and 4 South Courtyard – On-going
- Steel Studs Levels 1 – 5 North – On-going
- Exterior soffit steel stud framing North – On-going
- Exterior denseglass sheeting Levels 1 – 5 North – On-going
- Mechanical Rough-ins Parkade – Levels 5 – On-going
- Electrical Rough-ins Parkade – Levels 5 – On-going
- Exterior and Parkade soffit membrane North – On-going
- Steel Stud furring of columns and walls CRU 4 South – On-going
Key Achievement
- Suspended Roof Slab – Complete
Look Ahead
- Roofing Membrane Completion – October 11th
- TI Level 5 interior steel stud installation starting September 19th
Current Photos
Key Activities
Activities | Baseline Start Date | Baseline Finish Date | Revised Start Date | Revised Finish Date | Remarks |
Steel Studs Framing Levels 1 – 6 | 04/26/22 | 09/08/22 | 05/10/22 | 10/14/22 | In-progress |
Curtain walling Levels 1 – 6 | 02/21/22 | 05/10/22 | 04/29/22 | 10/21/22 | In-progress |
Plaster & Gypsum Board Install (BB) |
| 08/12/22 | 10/20/20 | In-progress | |
Membrane Roofing | 09/08/22 | 09/22/22 | 09/20/22 | 10/11/22 | In-progress |