Schedule Progress
  • Damp proofing – 95% Complete.
  • Level 6 suspended slab North – On-going
  • Level 6 suspended slab South – On-going
  • Backfilling – On-going
  • Upstand walls – On-going
  • Curtain walls Levels 1&2 CRU’s – On-going
  • Steel Studs Levels 1 – 4 – On-going
  • Brickwork Parkade – On-going

 

Key Achievement
  • Level 5 North East core wall 2 and columns – Complete

 

Look Ahead
  • Level 6 Suspended slab North-West and South – Completion June 14th
  • Level 6 Suspended slab North-East – Completion June 20th
  • Level 6 Columns and Core Walls – Completion June 30th
Upcoming Activities

Activities

Baseline Start Date

Baseline Finish Date

Revised Start Date

Revised Finish Date

Remarks

Level 6 Suspended Slab

05/07/22

05/21/22

05/17/22

06/20/22

In-progress

Steel Studs Framing Levels 1 – 4

01/06/22

01/19/22

04/26/22

07/07/22

In-progress

Curtain Wall Framing CRU’s 1 & 2

01/20/22

02/04/22

04/29/22

06/10/22

In-progress

Level 6 Core walls and Columns

12/13/21

12/28/21

06/21/22

07/05/22

 

Roof Slab

01/03/22

01/17/22

07/05/22

07/19/22