Schedule Progress
- Damp proofing – 95% Complete.
- Level 6 suspended slab North – On-going
- Level 6 suspended slab South – On-going
- Backfilling – On-going
- Upstand walls – On-going
- Curtain walls Levels 1&2 CRU’s – On-going
- Steel Studs Levels 1 – 4 – On-going
- Brickwork Parkade – On-going
Key Achievement
- Level 5 North East core wall 2 and columns – Complete
Look Ahead
- Level 6 Suspended slab North-West and South – Completion June 14th
- Level 6 Suspended slab North-East – Completion June 20th
- Level 6 Columns and Core Walls – Completion June 30th
Upcoming Activities
Activities | Baseline Start Date | Baseline Finish Date | Revised Start Date | Revised Finish Date | Remarks |
Level 6 Suspended Slab | 05/07/22 | 05/21/22 | 05/17/22 | 06/20/22 | In-progress |
Steel Studs Framing Levels 1 – 4 | 01/06/22 | 01/19/22 | 04/26/22 | 07/07/22 | In-progress |
Curtain Wall Framing CRU’s 1 & 2 | 01/20/22 | 02/04/22 | 04/29/22 | 06/10/22 | In-progress |
Level 6 Core walls and Columns | 12/13/21 | 12/28/21 | 06/21/22 | 07/05/22 | |
Roof Slab | 01/03/22 | 01/17/22 | 07/05/22 | 07/19/22 |